Dublin Core
Title
Box 17, Folder 7, Document 61
Text Item Type Metadata
Text
HEERY AND HEERY « FINCH, ALEXANDER, BARNES, ROTHSCHILD AND PASCHAL
Associated Architects and Engineers
Fifth Floor
70 Fairlie Street
Atlanta, Georgia 30303
404 524-1768
October 14, 1964
Mr. Arthur L. Montgomery
Atlanta & Fulton County Recreation Authority
The Atlanta Coca-Cola Bottling Company
864 Spring Street N. W.
Atlanta, Georgia 30308
PRIVILEGED
Weekly Construction Report RE: STADIUM
For Week Ending October 13, 1964.
ENCLOS URES : (8) Photographs each to: Mayor Allen
Mr. Montgomery
Mr - Lane
Heery & Heery
FABRaP
WEATHER: Wednesday October 7 Clear, 48° AM; Clear 650 PM
Thursday October 8 Clear, 46° AM: Clear 64° PM
Friday October 9 Clear, 50° AM; Clear 68° PM
Saturday October 10 Fair, 48° AM; fair, 57° PM
Sunday October 11 fair, 48° AM; fair, 66° PM
Monday October 12 Clear, 47° AM; clear 66° PM
Tuesday October 13 Partly cloudy, 54-1/2° AM
partly cloudy, 72° PM
CPM SCHEDULE:
182 days elapsed;
183 days remain.
This is the half-way point, and although we have
no CPM printout this week, progress seems satisfactory.
The General Contractor advised us today that Ingalis
is going on a three shift day and six day week until
further notice to insure performance of their schedule.
HEERY AND HEERY + FINCH, ALEXANDER, BARNES, ROTHSCHILD AND PASCHAL
Page 2
ACTIVITY: THOMPSON & STREET - (General Contractor)
Poured ramp wall 64-57/E at service level. Graded fill at
service level. Poured main concourse topping. Formed West
wall at pedestrian tunnel (partial). Poured lower level
seating risers 37-39, 32-34, 44-45, 47-48, 64-67,
68-76. (all partial). Setting precast seating units at
main concourse 45-54. Setting door frames at service level.
Poured precast units.
CECO
Removed ramp forms 21-26 service level.
WESTERN - (Waterproofing)
Waterproofed main concourse 36-39 (partial). Completed
waterproofing lower level. Waterproofed West end of
Pedestrian tunnel. Placed sealant in construction and
expansion joints at lower level seating risers.
DIXIE
Erected masonry 43-57/C-E at service level.
ROBERTSON
Installed metal deck at upper concourse 46-49, and at
Club Deck to 56.
INGALLS
Unloaded steel, erected upper seating bent at 45. Erected
ramp beams 41-43. Welded to 68. Columns to 77 and beams
to 75. Erected upper concourse framing 41-43.
GULF
Set reinforcing steel on metal deck at ramp slabs. Set
reinforcing steel in North wall service tunnel (partial).
Roughed in 6-7/C-D, 65-67/C-D, 48-50/C-D, 31-33/C-D at
service level. Roughed in at Club Deck.
HEERY AND HEERY + FINCH, ALEXANDER, BARNES, ROTHSCHILD AND PASCHAL
Page 3
ACTIVITY (cont.)
CLEVELAND
Conduit etc., in masonry walls and Club Deck, roughed
in 17-21/A-B at service level.
NORTH BROTHERS
Installing pipe insulation at service level.
AMERICAN SEATING
Drilling holes in Lower level seating risers.
HEERY & HEERY + FINCH ALEXANDER BARNES ROTHSCHILD & PASCHAL
F. William Mitchell
Project Manager
CC: Mayor Allen
Mr. Lane
Mr. Scarborough
Project Representative
FABRaP
H&H
hee
Associated Architects and Engineers
Fifth Floor
70 Fairlie Street
Atlanta, Georgia 30303
404 524-1768
October 14, 1964
Mr. Arthur L. Montgomery
Atlanta & Fulton County Recreation Authority
The Atlanta Coca-Cola Bottling Company
864 Spring Street N. W.
Atlanta, Georgia 30308
PRIVILEGED
Weekly Construction Report RE: STADIUM
For Week Ending October 13, 1964.
ENCLOS URES : (8) Photographs each to: Mayor Allen
Mr. Montgomery
Mr - Lane
Heery & Heery
FABRaP
WEATHER: Wednesday October 7 Clear, 48° AM; Clear 650 PM
Thursday October 8 Clear, 46° AM: Clear 64° PM
Friday October 9 Clear, 50° AM; Clear 68° PM
Saturday October 10 Fair, 48° AM; fair, 57° PM
Sunday October 11 fair, 48° AM; fair, 66° PM
Monday October 12 Clear, 47° AM; clear 66° PM
Tuesday October 13 Partly cloudy, 54-1/2° AM
partly cloudy, 72° PM
CPM SCHEDULE:
182 days elapsed;
183 days remain.
This is the half-way point, and although we have
no CPM printout this week, progress seems satisfactory.
The General Contractor advised us today that Ingalis
is going on a three shift day and six day week until
further notice to insure performance of their schedule.
HEERY AND HEERY + FINCH, ALEXANDER, BARNES, ROTHSCHILD AND PASCHAL
Page 2
ACTIVITY: THOMPSON & STREET - (General Contractor)
Poured ramp wall 64-57/E at service level. Graded fill at
service level. Poured main concourse topping. Formed West
wall at pedestrian tunnel (partial). Poured lower level
seating risers 37-39, 32-34, 44-45, 47-48, 64-67,
68-76. (all partial). Setting precast seating units at
main concourse 45-54. Setting door frames at service level.
Poured precast units.
CECO
Removed ramp forms 21-26 service level.
WESTERN - (Waterproofing)
Waterproofed main concourse 36-39 (partial). Completed
waterproofing lower level. Waterproofed West end of
Pedestrian tunnel. Placed sealant in construction and
expansion joints at lower level seating risers.
DIXIE
Erected masonry 43-57/C-E at service level.
ROBERTSON
Installed metal deck at upper concourse 46-49, and at
Club Deck to 56.
INGALLS
Unloaded steel, erected upper seating bent at 45. Erected
ramp beams 41-43. Welded to 68. Columns to 77 and beams
to 75. Erected upper concourse framing 41-43.
GULF
Set reinforcing steel on metal deck at ramp slabs. Set
reinforcing steel in North wall service tunnel (partial).
Roughed in 6-7/C-D, 65-67/C-D, 48-50/C-D, 31-33/C-D at
service level. Roughed in at Club Deck.
HEERY AND HEERY + FINCH, ALEXANDER, BARNES, ROTHSCHILD AND PASCHAL
Page 3
ACTIVITY (cont.)
CLEVELAND
Conduit etc., in masonry walls and Club Deck, roughed
in 17-21/A-B at service level.
NORTH BROTHERS
Installing pipe insulation at service level.
AMERICAN SEATING
Drilling holes in Lower level seating risers.
HEERY & HEERY + FINCH ALEXANDER BARNES ROTHSCHILD & PASCHAL
F. William Mitchell
Project Manager
CC: Mayor Allen
Mr. Lane
Mr. Scarborough
Project Representative
FABRaP
H&H
hee
Comments