Ho Fa Zimmerman
Je He Leopold
March 6, 1969
Atlanta Housing Authority - Jonesboro Road Project
December 2, 1968
Development Conference at HUD attended by representatives from AHA, HUD,
Architect, Contractor and Developere Changes suggested by HUD Technical
Review Branch were agreed upone
December 17, 1968
Forwarded to AHA modifications to Option Agreements covering the three
land parcels comprising site. Options extended from December 17, 196S to
April 10, 1969.
January 24, 196
Forwarded to AHA Memorandum of Understanding listing changes agreed upon
during December 2, 1968 Development Conference.
February 13, 1969
Forwarded drawings and outline specifications updated to reflect HUD and
AHA comments during December 2, 1968 Development Conference.
February 20, 1969
Forwarded to AHA survey plat and legal description of site property.
March 3, 1969
Received written comments from HUD Technical Review Branch on drawings and
specifications submitted February 13.
March 4, 1969
Engaged services of Pittsburgh Testing Laboratory to make soil investigation
of sites maport expected by March li.
Atlanta Housing Authority - Jonesboro Road Project (continued)
March 5. 1969
Conference at HUD to discuss comments received March 3. HUD agreed that
drawings and outline specifications as submitted, modified by written
comments, can be used for jetter of intents except site plan and storm
drainage plan which shall bo revised to reflect changes agreed upone
Both revised drawings will be delivered to AHA and HUD Monday, March
10, 1969. Soil investigation report scheduled for delivery not later
than March 17. These will complete documents required fer letter of
intente
Developer to contact Trust Company of Georgia immediately regarding
financing procedures. Also, attorneys will be given go ahead for title
policy and other legal documents required in connection with purchase of
property by Developere
Je He Leopold
March 6, 1969
Atlanta Housing Authority - Jonesboro Road Project
December 2, 1968
Development Conference at HUD attended by representatives from AHA, HUD,
Architect, Contractor and Developere Changes suggested by HUD Technical
Review Branch were agreed upone
December 17, 1968
Forwarded to AHA modifications to Option Agreements covering the three
land parcels comprising site. Options extended from December 17, 196S to
April 10, 1969.
January 24, 196
Forwarded to AHA Memorandum of Understanding listing changes agreed upon
during December 2, 1968 Development Conference.
February 13, 1969
Forwarded drawings and outline specifications updated to reflect HUD and
AHA comments during December 2, 1968 Development Conference.
February 20, 1969
Forwarded to AHA survey plat and legal description of site property.
March 3, 1969
Received written comments from HUD Technical Review Branch on drawings and
specifications submitted February 13.
March 4, 1969
Engaged services of Pittsburgh Testing Laboratory to make soil investigation
of sites maport expected by March li.
Atlanta Housing Authority - Jonesboro Road Project (continued)
March 5. 1969
Conference at HUD to discuss comments received March 3. HUD agreed that
drawings and outline specifications as submitted, modified by written
comments, can be used for jetter of intents except site plan and storm
drainage plan which shall bo revised to reflect changes agreed upone
Both revised drawings will be delivered to AHA and HUD Monday, March
10, 1969. Soil investigation report scheduled for delivery not later
than March 17. These will complete documents required fer letter of
intente
Developer to contact Trust Company of Georgia immediately regarding
financing procedures. Also, attorneys will be given go ahead for title
policy and other legal documents required in connection with purchase of
property by Developere